Road Closures

FM2100 proposed work

This proposed work will be to: (The work will be broken up in sections as shown below)

  1. mill the old asphalt off the old roadway,
  2. repair the old roadway,
  3. widen a small portion of the roadway from S Diamondhead to Hare Road
  4. replace with new asphalt and striping on the roadway.

The total limits of the asphalt work will be from US90 to .66 miles south of Huffman Cleveland road.

The durations may be modified due to weather conditions.

US 90 to 1st Street

Beginning September 22, 2013 to October 16, 2013 (Sunday night thru Thursday night) from 9:00 pm to 5:00 am there will be nightly lane closures on FM2100 between US90 and 1st Street.

The Contractor (Angel brothers) will begin at US90 going northbound and mill out the existing asphalt in preparation for placement of new asphalt.

S Diamondhead to FM1960

 Beginning October 7, 2013 to December 9, 2013 the Contractor will be closing alternate lanes performing roadway work.

The alternate lane closure will only leave one lane open to traffic during the times of closures because of the existing 2 lane roadway.  (Police, Fire and Medical will have priority during these times)

FM1960 to .66 miles South of Huffman Cleveland

December 2, 2013 to January 24, 2013 the Contractor will be closing alternate lanes performing roadway work.

The alternate lane closure will only leave one lane open to traffic during the times of closures because of the existing 2 lane roadway.  (Police, Fire and Medical will have priority during these times)

 